Policies and Procedures Manual 2024 - 2025

10.8 - Budget and Program Revisions Policy

It is the policy of the University to report deviations from budget or project scope or objective. It is also the policy of the University to request prior approval from Federal awarding agencies for any of the following program or budget revisions:

  1. Change in the scope or the objective of the project or program (even if there is no associated budget revision requiring prior written approval).
  2. Change in a key person specified in the application or the Federal award.
  3. The disengagement from the project for more than three months, or a 25 percent reduction in time devoted to the project, by the approved project director or principal investigator.
  4. The inclusion, unless waived by the Federal awarding agency, of costs that require prior approval in accordance with Subpart E—Cost Principles (2 CFR Part §200.407).
  5. The transfer of funds budgeted for participant support costs as defined in §200.75 Participant support costs to other categories of expense.
  6. Unless described in the application and funded in the approved Federal awards, the subawarding, transferring or contracting out of any work under a Federal award. This does not apply to the acquisition of supplies, material, equipment, or general support services.
  7. Changes in the amount of approved cost-sharing or matching provided by The University.
  8. The need arises for additional Federal funds to complete the project.

 

The Federal awarding agency may, at its option, restrict the transfer of funds among direct cost categories or programs, functions and activities for Federal awards in which the Federal share of the project exceeds the Simplified Acquisition Threshold and the cumulative amount of such transfers exceeds or is expected to exceed 10 percent of the total budget as last approved by the Federal awarding agency. The Federal awarding agency may stipulate in the grant documents a higher percentage threshold at which prior approval is needed for budget line-item transfers, such as 25 percent of the total budget. The Federal awarding agency cannot permit a transfer that would cause any Federal appropriation to be used for purposes other than those consistent with the appropriation.